Every day, we influence our experience to continuously improve the performance of our customers’ wind power plants. We do this through the monitoring and performance diagnostics of wind turbines round the clock 24 x 7.
The continuous stream of data from our installed wind turbines enables us to meticulously plan and carry out service inspections, thereby reducing wind turbine down-time to an absolute minimum.
- Signs up PASL for 2MW at Motagunda, JAMNAGAR.
- 60MW P.E. Permission received from RRVPN – Rajasthan
- Identified 20MW site in Maharashtra.
- Total 20.7MW completed at Vinjalpur-JAMNAGAR.
- Successfully Commissioned 12MW (1.5MW 8WTG SUZLON) at Vinjalpur, JAMNAGAR.
- GAMESA’s 4MW (2WTG 2MW) ordered received and commissioned at Motagunda, JAMNAGAR.
- 79.5MW project of GAMESA at Jaisalmer, Rajasthan completed.
- 20MW additional P.E. permission received for Jaisalmer, RAJASTHAN.
- Identified 90MW site at RAJASTHAN.
- Signs up PASL for 4.2MW at Motagunda, JAMNAGAR. Successfully commissioned 4.2MW.
- Joined hand with SUZLON for its project of 35.7MW at Vinjalpur, JAMNAGAR. Successfully commissioned 4.2MW of SUZLON.
- GAMESA 56.1MW Commissioned at Jaisalmer, RAJASTHAN.
- Received additional 15MW P.E. permission for Motagunda, JAMANAGAR from GETCO.
- Set up 35MW substation at Vinjalpur, JAMNAGAR.
- Signs up GAMESA for 79.5MW at Jaisalmer, RAJASTHAN.
- Successfully commissioned 20.4MW at Jaisalmer, RAJASTHAN.
- Crosses 100MW installation mark.
- Additional 5.6MW P.E permission received from GETCO at Motagunda, Jamnagar.
- Set up 30MW substation at Motagunda, JAMNAGAR.
- Signs up GAMESA for 29 850kw machine, successfully commissioned 24.85MW at Motagunda site JAMNAGAR.
- Established Veer Enterprise GmbH in Stuttgart, GERMANY for exposure in global market.
- Acquired land and necessary permission from Government to set up 79.5MW at Jaisalmer, RAJASTHAN.
- Set up OWN wind farm at KUTCH, consist of 6 WTG of SWL make 1.35MW.
- Received order and successfully commissioned 6MW of GWL and SWL.
- Successfully done O & M activity for 30 MW wind farm as well as for 55 MW substation at KUTCH.
- Received order from SWL to develop infrastructure for 2.7MW in TAMIL NADU. Successfully completed it within 2 months.
- SWL 79 WTG successfully commissioned in record 75 days at KUTCH site.
- First Site identified for 55MW at KUTCH and duly received the approvals
- Received order from Elecon Engineering ltd. for 7.2MW Power Evacuation & Land.
- Successfully commissioned 55MW Substation at KUTCH.
- Signs up Southern Wind farms Ltd. 22MW wind power project complete infrastructure development ( Land, P.E., Civil Foundation, Transmission Line, Erection, Commissioning and O & M )